The Smart Guide for Home Builders

The Smart Guide for Home Builders

Home  ›  The Smart Guide for Home Builders
Second Edition · October 2026

The Smart Guide for Home Builders: from Plot to Move-In in Saudi Arabia

The Smart Guide for Home Builders explains the stages of building a home and the decision to make at each one in Saudi Arabia: the plot and soil testing, design and the building permit, the contractor and the contract, supervision, handover and maintenance. It was written by Dr. Abdulrahman Saeed Aldossary and is published by Innovative Standards Engineering Consulting Company in Al Khobar.

30 pages · PDF · direct download, no sign-up · Last updated: 1 November 2026
The Smart Guide for Home Builders, second edition cover

What this guide is and who it is for

For many families, building a home is the largest financial decision they will ever make. What we have seen across our projects is that most losses come from information that was missing at the right moment: a plot bought before its soil was tested, drawings built without being reviewed, or a contract written in a hurry.

It is the home building guide we give our own clients before they start. The first edition, published in March 2026, was a short summary of what an owner needs before starting. The second edition was rewritten as a practical guide you can return to at every stage, from the first question you ask yourself until after you move in. It is written for the owner and needs no engineering background.

What is new in the second edition

  • A map of the whole building journey on one page.
  • Checklists for the plot, drawings, contract, construction and handover.
  • What is specific to the Eastern Province: soil, groundwater, salts, and some neighborhood requirements.
  • The regulatory documents for the building permit and the occupancy certificate.
  • An annual maintenance calendar suited to the region’s heat and humidity.

The second edition was announced on LinkedIn on 4 November 2026: the author’s post and the company’s post.

How to use it

  • Read it once in full to see the project from start to finish.
  • Return to each part when you reach its stage.
  • The empty boxes next to items in the PDF are intentional: print the page and tick what you have done, or send it to your engineering office and ask about every item.

Notice and disclaimer: This guide is for awareness only and does not replace official regulations or an engineer who studies your case. Requirements change and differ from place to place, and the information here is current as of October 2026, so consult an engineering office and the competent authority before any decision. The company and the author accept no liability for any decision based on this guide alone.

Steps to building a house: the journey in eight stages

Each stage builds on the one before it, and a mistake left in one stage is paid for twice in the next.

StageThe key decision
1. Decision and budgetYour family’s needs now and in ten years, and a realistic budget ceiling with a reserve.
2. Plot and soilThe plot’s building regulations, its level, and a soil report before purchase if possible.
3. DesignAn architectural plan for your family, then the façade, then structural, electrical, mechanical and energy-efficiency drawings.
4. PermitUploading the drawings to the platform with the supervising office contract, the contractor contract and the other documents.
5. ContractingComparing bids priced on a single bill of quantities, and one written contract with payments tied to progress.
6. ShellExcavation, foundations, columns and slabs, and no pour before the supervising engineer approves the reinforcement.
7. FinishesInsulation and services first because they get buried, then the visible finishes.
8. Handover and move-inTests before handover, the occupancy certificate and as-built drawings, then routine maintenance.

Durations vary widely from one project to another, but design and permitting alone usually take months. Start them early, and do not tie your move-in date to an optimistic schedule.

01

Part One: Before You Buy the Plot

The most important project decisions are made before a single line is drawn. Will you build or buy? How much can you really spend? Then comes the plot.

Build it yourself or buy a ready home?

There is no single answer for everyone. The decision depends on your time and budget, and on whether you are ready to follow a project that runs for months.

CriterionBuilding yourselfBuying ready
Design controlFull: the plan is tailored to your familyLimited to what is on offer
Time to move inLonger: design, permit and constructionMuch shorter
Effort and follow-upContinuous follow-up by you or your representativeLess effort, focused on inspection before purchase
Quality visibilityYou see it stage by stage, and witness what gets buried before it is coveredWhat lies under the finishes is unseen, so you rely on the developer and on inspection
Biggest riskBudget and schedule overruns if planning or supervision is weakHidden defects in the structure, insulation or services
SuitsThose with time and a clear vision of their homeThose who need to move in soon, or have found a trusted developer

If you choose to build, Parts One, Two and Three are for you. If you choose to buy, go to inspecting a ready home before you buy: the inspection costs little compared with fixing a defect discovered after you move in.

Questions to answer before any step

A good home is one that fits your family’s life and means; it may not be the biggest. Many building problems start because these questions were not answered clearly before design.

  • Family: How many members are there now, and how many in ten years? Do elderly relatives live with you who need a ground-floor room, or a lift later? How many bedrooms do you really need, and which need an en-suite bathroom?
  • Hospitality: A majlis for men and another for women, or a single majlis? Do you need a separate guest entrance away from family circulation?
  • Work and service: A study or home office? A room for domestic staff or a driver, or a separate annex? A storeroom and laundry of sufficient size?
  • Outdoors: A garden that will actually be used, or low-maintenance outdoor areas? How many parking spaces? A pool now or later?

The real budget: what most owners forget

  • Design, reports and permit fees.
  • Engineering supervision throughout construction.
  • Electricity, water and sewer connections.
  • Boundary wall, gates and garden.
  • Kitchen, air conditioners and water heaters.
  • Furniture, curtains and decorative lighting.

A reserve of at least 10% of the construction cost for unexpected items is recommended. A project that starts with its budget already exhausted on paper usually stops halfway.

What determines the cost to build a villa?

The cost to build a villa is not set by the price per square metre alone. What changes it most: the built area the plot regulations actually allow, the soil and any extra fill or foundation waterproofing it needs, the level of finishes, which in many villas comes close to the cost of the shell or exceeds it, and the items most owners forget in the list above. So build your budget on a bill of quantities from your own drawings, not on an average price you heard.

Choosing the plot: a checklist before you buy

Do not judge a plot by its price before you know its soil and its building regulations; a cheap plot can later cost you more than the price difference.

  • Building regulations for the plot: permitted use, number of floors, setbacks and building coverage ratio. These figures decide the area you will actually build, so ask for them before you buy.
  • Title deed and boundaries: an updated electronic deed, and a land survey that matches the boundaries on site.
  • Shape and dimensions: a regular plot is easier to design and wastes less than a triangular or long, narrow one.
  • Streets and orientation: the number and width of streets, the orientation of the main façade to the sun and wind, and their effect on privacy and cooling.
  • Level: a plot lower than the street needs fill and rainwater drainage; a plot much higher needs steps and ramps.
  • Soil: was the plot a dumping ground for debris? Is it near the coast or a sabkha area?
  • Services: availability of electricity, water and sewerage, and proximity to schools, mosques and main roads.
  • Neighborhood requirements: some neighborhoods and subdivisions have their own conditions for façades, heights and materials, such as the Ajyal (Aramco) neighborhood in Dhahran.

Soil test and soil investigation, and what is different in the Eastern Province

A soil investigation report from an accredited laboratory is what the structural engineer uses to choose the type and depth of foundations, and it is usually among the documents the municipality requires to issue a building permit. Ideally order it before buying the plot, if the seller allows; in all cases before structural design.

What the report tells you

  • Soil layers down to the required depth.
  • The soil’s bearing capacity.
  • The groundwater level.
  • Salt content, including sulphates and chlorides.
  • The recommended foundation type and depth.

In parts of the Eastern Province, especially near the coast, you may find sabkha soil, groundwater close to the surface, and high salt levels in soil and water. These conditions do not prevent building, but they change its design and cost. The main changes:

  • Full waterproofing of foundations and all elements buried below ground.
  • Sulphate-resistant cement when the report recommends it.
  • Adequate concrete cover around reinforcing steel to protect it from corrosion.
  • Replacing weak soil, or dewatering during excavation in some cases.

An example with hypothetical figures: two adjacent plots in the same neighborhood, each 600 m², the second cheaper by SAR 60,000. The owner bought it, then the soil report showed the need for an extra fill layer 2.5 m deep. He had to import selected soil and spread it under the building in layers, each compacted and tested before the next, with extra waterproofing for the foundations. In this example that cost about SAR 70,000, which is SAR 10,000 more than he saved on the price, plus a one-month delay. Actual costs vary with the site and the soil report.

The rule: never start building without a soil report, and never accept a structural design that was not based on the report for your own plot.

02

Part Two: Design and Permitting

A good plan saves many times its cost during construction. This is where your family’s needs become drawings that are permitted and built as drawn.

Design starts from your family’s life

A common mistake is for an owner to bring an online plan and ask for it to be built as is. A ready-made plan does not know your plot, its orientation or its building regulations, and it does not know how your family lives day to day. Use ideas from other projects as inspiration, and give the designer an honest picture of your day. For more detail, see residential design in Al Khobar.

Review in the plan before approving it

  • Separation of guest and family circulation.
  • Clear room dimensions after furniture is placed.
  • Locations of outdoor AC units and water tanks.
  • Storage space, the first thing to be forgotten.
  • Daylight in the main rooms, and shading from the western sun.
  • Room to expand later, or a space for a future lift.
Main entrance and interior staircase of a residential villa in Al Jamiah, Dhahran
Main entrance and interior staircase, Al Jamiah district, Dhahran · one of our interior designs

Architectural identity and neighborhood requirements

In the Eastern Province, the architectural style of the façade has become a permit requirement. The Saudi Architecture Map, launched in March 2025, includes 19 styles, four of them in the region: East Coast architecture in Al Khobar, Dammam, Dhahran and Jubail; Qatif architecture; Al-Ahsa Oasis architecture; and Eastern Najdi architecture.

The guidelines were applied to government and commercial projects in October 2025, then to all residential projects in the East Coast and Qatif styles in November 2025, and then in the Al-Ahsa and Eastern Najdi styles in April 2026, through the Balady platform.

Your plot’s location determines the style; what you choose is the level of treatment: traditional, transitional or contemporary, and contemporary is the most used in new projects. A plan that does not follow the style is returned by the municipality for revision, so it should be settled before any drawing. The guidelines do not apply to renovating existing buildings or adding to them.

Some neighborhoods have their own conditions on top of the Saudi Building Code. From our experience: we have designed more than 70 projects in Ajyal 1 and Ajyal 2 in Dhahran to Aramco specifications, covering architectural and interior design, façades and landscaping. A façade that breaks the conditions may be rejected or have to be rebuilt.

Following the style does not raise the cost if it enters the design from the start, because proportions, openings and massing are decisions on paper. The difference comes from materials: natural stone costs more than other finishes, but it withstands coastal humidity and salinity for longer.

Villa in the East Coast architectural style in Al Sadafah, Al Khobar
Villa in the East Coast style, Al Sadafah, Al Khobar
Outdoor seating under a shaded pergola in Al Qusur, Al Khobar
Seating under a shaded pergola, Al Qusur, Al Khobar

The drawings package: what you receive and what to review

The architectural plan alone is not enough to build. This is the full package you should receive before contracting a builder:

DrawingWhat it containsAsk about
ArchitecturalFloor plans, elevations and sections, and finish, door and window schedulesClear dimensions, door swing directions, and wardrobe and AC locations
Façade and wallMain façade and boundary wall design with a 3D viewMaterials and colours, and compliance with neighborhood requirements
StructuralFoundations, columns, beams and slabs to the Saudi Building CodeIs it based on your plot’s soil report? What is the foundation waterproofing detail?
ElectricalLoad distribution, lighting, sockets, earthing and low currentKitchen and bedroom sockets, and provisions for cameras, solar panels and an EV charger
MechanicalWater supply, drainage and ventilationDrainage falls, tank and heater locations, and roof and rainwater drainage
Energy efficiencyInsulation of external walls and roofs, glazing and window typeInsulation type and thickness, per residential energy conservation requirements (SBC 602)

Have drawings from another office? Ask for the editable DWG files alongside the PDFs; you will need them for any later change, for interior design or for a garden. An engineering design review before permitting or construction reveals clashes between disciplines while they are still on paper, where they are cheapest to fix.

Ask the office before you sign the design contract

  • How many plan proposals and how many revision sessions are included? What does an extra session cost?
  • Are structural, electrical, mechanical and energy-efficiency design included, or under separate contracts?
  • Is uploading the drawings to the platform included in the contract?

Building permit in Saudi Arabia: how to get it, parties and documents

Building permit applications are submitted electronically by an accredited engineering office through the Balady platform; the Riyadh municipality has its own portal. In most cases the permit is issued only after a supervising engineering office and a contractor have been appointed.

Documents usually required

  • Updated electronic title deed.
  • Survey decision or report for the plot.
  • Soil investigation report from an accredited laboratory.
  • Architectural, structural and other required drawings.
  • Design office contract.
  • Supervising office contract (it may be the design office).
  • Contract with a classified contractor.
  • Latent defects insurance policy, for buildings that require it.

The latent defects insurance policy is requested by the contractor through Balady from an insurance company. It covers hidden structural defects that affect the building’s safety, usually for ten years, and does not cover finishes. The list varies by municipality and building type, and the competent authority has the final word.

PartyRole in the project
OwnerDefines needs and budget, signs contracts, and approves drawings and changes in writing
Design officePrepares all drawings and uploads them for the permit application
Supervising officeFollows construction stage by stage, approves work before it is covered, and submits supervision reports
ContractorBuilds to the permitted drawings and the contract, and requests the insurance policy when required

Before you apply: make sure the drawing you upload is the one you will actually build. Any difference between what is permitted and what is built can hold up the occupancy certificate at the end of the project, and may later hold up a sale or financing.

03

Part Three: Contracting and Construction

This is where most of the budget is spent and where the big mistakes happen. A clear contract and present supervision are what keep a project on time and on budget.

Choosing the contractor: technical and financial evaluation

Choosing a contractor on total price alone is one of the costliest decisions; a very low bid may mean missing items or a misjudgement you will pay for during construction as extra claims or stoppages. The safest way: ask three contractors to price a single bill of quantities taken from your drawings, then compare the bids item by item before you look at the total.

Technical evaluationFinancial evaluation
Visit at least two of their completed projects, preferably with an engineerA detailed bid with unit rates, not a lump sum on one line
Check their commercial registration, and their registration and classification with the Saudi Contractors AuthorityCompare quantities and specifications in the bids before prices
Ask: who will be on site daily, and who checks quality?A reasonable advance payment, with the rest tied to progress
How many projects are they running now, and do they have enough labour and equipment?What is excluded from the bid? Get it in writing

Warning signs: a bid far below the others without a convincing explanation, a large advance payment before any work on site, refusal to write specifications and brands into the contract, or “we’ll take care of everything” said verbally without a written clause.

How to read a bill of quantities: it turns drawings into items: cubic metres of concrete, square metres of blockwork, plaster and tiles, and electrical and plumbing points. When the quantities are the same in every bid, the difference in unit rates becomes clear, and you see where each contractor raised or lowered their price.

The construction contract: clauses you should never give up

The construction contract is the only document you can refer to when the parties disagree, and a verbal agreement does not protect you when small details turn into financial claims.

  • Scope of work, with the approved drawings as its reference.
  • Specifications: materials, brands and grades.
  • Bill of quantities and unit rates.
  • A time schedule with clear stages.
  • Payments tied to progress accepted on site.
  • Retention released after final handover.
  • Delay penalty and its maximum.
  • Variation orders: no change unless written, with an agreed price before execution.
  • Exclusions stated explicitly.
  • Warranties: structure, waterproofing and services.
  • Site responsibility: safety, waste and damage to neighbours.
  • A dispute resolution mechanism before going to court.
Neoclassical dining room of a private palace in Al Corniche, Al Khobar
Neoclassical dining room for a private palace, Al Corniche, Al Khobar · one of our interior designs

The structure: what to inspect before every pour

Excavation, footings, columns, beams and slabs are the building’s real skeleton, and any weakness in them affects its whole safety. Concrete cannot be inspected from the inside once poured, so inspection belongs before the pour.

StageWhat to check before moving on
ExcavationReaching the layer and depth specified in the soil report, a clean formation level, and dewatering if water appears
FootingsFooting sizes and positions per the grid lines, bar diameters and spacing, and concrete cover using spacers
Necks and tie beamsWaterproofing of everything buried below ground, then backfilling and compaction in layers
Ground slabTermite treatment, and drainage pipes under the slab, tested
ColumnsGrid lines matching the drawing, vertical alignment, and stirrup spacing
SlabsFormwork strength and level, reinforcement, electrical and plumbing services before the pour, and taking concrete cube samples

Eastern Province summers and concrete: in extreme heat, the water in concrete evaporates quickly. Pouring during the hottest hours without precautions, or neglecting curing with water or covers in the days after the pour, weakens the concrete and causes surface cracks. Ask the contractor for the curing plan before every pour.

Tests to request: cube samples from every major pour with results at 7 and 28 days, certificates of conformity for the reinforcing steel and cement supplied, and a compaction test for the fill under the ground slab.

The rule: no concrete is poured before the supervising engineer approves the reinforcement.

During construction: where the big mistakes happen

Most construction mistakes happen on site, and their causes repeat in almost every project: changes decided on site, weak follow-up, and rushing to gain a few days.

  • Structural changes: moving a column, removing a beam or cutting an opening in a load-bearing wall look small on site but can affect the safety of the whole building. Any structural change goes back to the engineering office before it is made.
  • Rushing: striking formwork early, pouring before the reinforcement is approved, or finishing over insulation that has not been tested. The days gained here are paid for later with weeks of repairs.
  • Unwritten changes: “change it and we’ll sort it out later” is the start of an almost certain dispute. Every change is written down with its price and duration before it is made.
  • Supervising the finishes: supervision of the shell is a regulatory requirement; supervision of the finishes is optional, yet that is where most disputes between owners and contractors arise.

Document everything: a weekly photo record of the site, photos of every element before it is covered, written minutes of every supervision visit, and one communication channel for you, the contractor and the supervisor.

Supervision visits not to be missed: approval of the excavation level and formation, reinforcement before every pour, waterproofing before backfilling, services before plastering, bathroom waterproofing test before tiling, and roof waterproofing and falls before final finishes. More in engineering supervision in Al Khobar.

Shell and finishes: what gets buried cannot be changed

Many believe the shell is the most expensive part of a build, but in many villas the finishes come close to its cost or exceed it. Even so, the shell remains the most important for safety, and saving on it is never advisable.

Do not save on these itemsWhere can you save?
Waterproofing of foundations, bathrooms, kitchens and the roofItems that are easy to upgrade later, such as decorative light fittings
Thermal insulation of external walls and roofs per energy-efficiency requirements; its effect shows in the electricity bill every summerBuilding the garden in phases after moving in
Plumbing and electrical services: approved materials and a pressure test before closing upFewer different materials, since each new material means more waste and detailing
Rainwater drainage: roof falls and drainsSettling materials and colours in the interior design before buying, so you buy the right quantities once

Everything in the first column disappears behind tiles and gypsum, and fixing it after moving in means breaking things open.

Bedroom with a marble feature wall in Al Andalus, Al-Ahsa
Bedroom with a marble wall, Al Andalus, Al-Ahsa
Inner courtyard with a wall waterfall in Danat Al Ramis, Qatif
Inner courtyard with a wall waterfall, Danat Al Ramis, Qatif

Handover and the occupancy certificate: when it is issued and what it requires

Do not sign the final handover or release the last payment before going through this list with the supervising engineer.

Tests and inspection

  • Pressure test of water pipes, and leak check.
  • Flood test of bathrooms and the roof before handover.
  • Operating every electrical circuit and breaker, and checking earthing.
  • Floor and roof falls towards the drains.
  • Doors and windows: closing, sealing and insulation.
  • Air conditioning, water heaters and pumps under actual operation.

Documents to receive

  • As-built drawings, as actually built on site.
  • Warranty certificates and appliance manuals.
  • Signed handover minutes and the list of outstanding snags.
  • Latent defects insurance policy, if issued.
  • All keys and system codes.

The occupancy certificate is the current name on the Balady platform for what owners knew as the building completion certificate. The supervising engineering office submits the application with its reports, and the building must comply with the permit and with the Saudi Building Code, including thermal insulation and fire safety. A permanent electricity connection requires it in most cases, so any difference between what was permitted and what was built shows up here, and may delay your move.

After handover: agree a maintenance warranty period with the contractor, record every issue that appears during it with its date and photo, and notify the contractor in writing before the period ends. The retention held in the contract is what ensures the contractor comes back.

04

Part Four: Ready Homes and Maintenance

If you are buying a ready home, or have just moved into your new one, this part is for you: what to inspect before buying, when renovation makes more sense, and how to keep your home in good shape for many years.

Inspecting a ready home before you buy

An inspection cannot give you complete certainty about what lies behind the walls, but it reduces the risk considerably. It is best done with an engineer or a specialised inspection company.

  • Structure: diagonal or horizontal cracks in walls and ceilings, which are more serious than hairline cracks in paint; settlement in floors, or doors that do not close properly; visible rust on ceilings or columns.
  • Services: close every tap and watch the water meter; if it moves, there is a leak. Check the electrical panel’s arrangement, earthing and hot breakers, and the water pressure on upper floors.
  • Moisture and insulation: stains or peeling paint at the bottom of walls and around bathrooms, a damp smell in closed rooms, and the condition of the roof: waterproofing, falls and drains.
  • Documents: building permit and approved drawings, occupancy or completion certificate, soil report if available, latent defects insurance and its remaining term, and whether the building matches the drawing: is there an unpermitted annex or extra floor?

Ask the seller about the construction date, the contractor and the supervising office, any past leaks or repairs, and anything added after the permit; hesitant answers deserve a closer inspection. If you are buying off-plan, check that the project is licensed for off-plan sale under the Wafi programme, and read the handover specifications in the contract item by item.

Renovate or rebuild?

Renovation can be an excellent option, or it can turn into a project more expensive than building new. Answer these questions before you decide:

  1. Is the structure sound? Ask for a structural assessment first; the answer may settle the decision on its own.
  2. How old are the electrical and plumbing services? Replacing them means breaking up floors and walls.
  3. Does the current layout meet your family’s needs, or will you change the whole arrangement of spaces?
  4. What does a full renovation cost compared with demolition and rebuilding, once you add the cost of living elsewhere in the meantime?

Modern systems and alternative materials: use what is proven in your main home, and before any new material ask whether it is approved and compliant with the Saudi Building Code, and who will maintain it locally in five years. Worth providing for now: conduits for rooftop solar panels, an EV charging point, and cabling for cameras, networks and a smart home. Providing for them during construction costs little; adding them after finishing is expensive.

The annual maintenance calendar

Most building problems start with a small fault that is ignored: a minor leak turns into damp, then into corrosion of steel and concrete. In the Eastern Province, heat, humidity and salts add extra strain on every element of the house.

WhenWhat to do
Before summer (March and April)Service the air conditioners, clean their filters and outdoor units, and check the roof waterproofing before the hottest months
Before the rainy season (October and November)Clean roof drains and downpipes, and check the joints around external windows and doors
Every yearTermite inspection, cleaning and disinfecting water tanks, checking the electrical panel, and renewing the silicone around basins and bathtubs
Every 3 to 5 yearsAssess the roof waterproofing layer and renew it according to its type, and maintain external paintwork affected by humidity and salts
ImmediatelyAny new leak, damp patch or crack; early repair is always cheaper than delay

Signs that call for an engineer without waiting: a crack that widens over time, a door that suddenly starts rubbing against its frame, rust on a ceiling, damp returning to the same spot after repair, or settlement in the floors.

Construction mistakes: ten costly errors and how to avoid them

These mistakes repeat in building projects more than any others, and every one of them can be avoided with a decision made at the right time:

  1. Buying a plot before knowing its building regulations and soil.
  2. Starting without a clear budget ceiling and without a reserve for unexpected items.
  3. Building a ready-made plan from the internet as is, without a design that fits your plot and family.
  4. A structural design not based on your plot’s soil report.
  5. Choosing the contractor on total price alone, without comparing items and specifications.
  6. A contract without a bill of quantities and specifications, with payments tied to dates instead of progress.
  7. Saving on the structure and insulation, which can only be fixed after moving in by breaking things open.
  8. Structural changes on site without going back to the engineering office.
  9. Pouring concrete before the supervising engineer approves the reinforcement.
  10. Postponing the repair of leaks and damp after moving in.

If you remember only one thing: start from your real needs before the look of the façade, put every agreement in writing, and let nothing be buried before an engineer has seen it.

05

Part Five: How We Support You

We design for clients across Saudi Arabia and the Gulf states, and supervise construction in Al Khobar, Dammam, Dhahran and Qatif.

Our services at every stage

Each stage of this guide corresponds to specific engineering work. These are our services in project order; each links to its own page:

We measure client satisfaction at three points: after the consultation, monthly during the project, and after completion. Our drawings are approved by engineers licensed by the Saudi Council of Engineers, and we do not tie you to a particular contractor.

First Edition · March 2026

The Smart Guide for Home Builders, first edition cover

The first edition, “The Smart Guide for Home Builders: a practical summary for building a successful home and avoiding costly mistakes”, runs to 20 pages. It covers building yourself or buying ready, decisions not to postpone, choosing the plot, design and drawings, soil testing, the structure, choosing the contractor, the contract, construction mistakes, and shell and finishes. The second edition expands these topics and adds permitting, handover, the occupancy certificate and maintenance.

About the author and publisher

Dr. Abdulrahman Saeed Aldossary is the CEO of Innovative Standards Engineering Consulting Company. He holds a PhD in engineering from the University of Birmingham, is a professional engineer registered with the Saudi Council of Engineers, and has more than 25 years of experience in project management and engineering infrastructure.

Innovative Standards Engineering Consulting Company is an engineering consultancy based on Prince Turkey Street, Corniche, Al Khobar. It designs for clients across Saudi Arabia and the Gulf states and supervises construction in Al Khobar, Dammam, Dhahran and Qatif, with more than 130 projects since 2024 and a 5.0 rating from more than 70 reviews on Google Maps.

To cite this guide: Aldossary, Abdulrahman Saeed. The Smart Guide for Home Builders, 2nd ed., October 2026. Al Khobar: Innovative Standards Engineering Consulting Company. https://innostandards.com/en/smart-guide-for-home-builders/

Frequently asked questions

How do I get a building permit in Saudi Arabia?

The application is submitted electronically by an accredited engineering office through the Balady platform, with the drawings, an updated title deed, a survey report and a soil investigation report. In most cases the permit is issued only after a supervising engineering office and a classified contractor have been appointed; the Riyadh municipality has its own portal.

Where and when should I do a soil test?

A soil test is carried out by an accredited laboratory, ideally before buying the plot if the seller allows, and in all cases before structural design, because the type and depth of foundations are based on its results.

What determines the cost to build a villa?

The built area the plot regulations allow, the soil, the level of finishes, and items outside the price per square metre such as design, supervision, utility connections, the boundary wall, kitchen and air conditioning. A reserve of at least 10% of the construction cost is recommended for unexpected items.

What is The Smart Guide for Home Builders?

A practical guide by Dr. Abdulrahman Saeed Aldossary that explains the decisions to make at each stage of building a home in Saudi Arabia: plot and soil, design and permitting, contracting and construction, handover and maintenance. The second edition was published in October 2026 and runs to 30 pages, in Arabic and English.

Do I need to register to download the guide?

No. Click the download button and the PDF downloads directly.

What are the costliest home building mistakes?

Among the costliest: buying a plot before knowing its regulations and soil, starting without a clear budget and reserve, choosing the contractor on total price alone, a contract without a bill of quantities and specifications, and pouring concrete before the supervising engineer approves the reinforcement.

What documents are needed for a building permit in Saudi Arabia?

Usually: an updated electronic title deed, a survey report, a soil investigation report, architectural, structural and other drawings, the design office contract, the supervising office contract, a contract with a classified contractor, and a latent defects insurance policy for buildings that require it. The list varies by municipality and building type.

What is the occupancy certificate?

It is the current name on the Balady platform for the building completion certificate. The supervising engineering office submits the application, the building must comply with the permit and the Saudi Building Code, and a permanent electricity connection requires it in most cases.

Does the guide replace an engineering office?

No. The guide helps you ask the right questions and decide at the right time, but design and supervision need a licensed engineering office that studies your case and follows your project.

What are the stages of building a home, in order?

Eight stages: decision and budget, plot and soil, design, permit, contracting, structure, finishes, then handover and move-in. Each stage builds on the one before it, so a mistake left in one stage costs double in the next.

How do I choose a building contractor?

Ask three contractors to price the same bill of quantities taken from your drawings, and compare items and specifications before the totals. Visit two of their finished projects and check their classification with the Saudi Contractors Authority.

Which clauses must a construction contract include?

Scope of work and the approved drawings, specifications and brands, a bill of quantities with unit rates, payments tied to completed work, and a retention held until final handover. Add one more: no change without a written order priced before it is built.

Want an engineer’s view on your project?

A one-hour first consultation at our Al Khobar office or remotely, to review your plot, your family’s needs and your budget before any commitment.

Start a WhatsApp chat Book a consultation
★★★★★ 5.0 · from more than 70 reviews on Google Maps
  • A licensed and classified Saudi company